(1) Approval of a Type III application shall not expire except as provided in subsections (2) through (4). If an approval of a Type III application has expired according to any of the conditions stated in subsections (2) through (4), the original application approval is revoked.

(2) Unless the hearings official designates otherwise, a conditional use permit approval shall expire 18 months after the effective date of approval unless actual construction or alteration has begun under a required permit, or in the case of a permit not involving construction or alteration, actual commencement of the authorized activity has begun. However, the applicant may submit a modification application at any time before the 18-month period has expired, requesting an extension of the approval period. The applicant may request more than one extension. Under no circumstances, however, can the total combined extension periods exceed 36 months from the original expiration date.

(3) A planned unit development tentative plan approval shall expire if the applicant fails to submit a planned unit development final plan application in accordance with the schedule approved at the time of tentative plan consideration. In the absence of a specified schedule, the tentative plan approval shall expire 18 months after the effective date of tentative plan approval.

(4) Unless the decision specifies otherwise, a Willamette River Greenway Permit approval shall expire 18 months after the effective date of approval unless actual construction or alteration has begun under a required permit, or in the case of a permit not involving construction or alteration, actual commencement of the authorized activity has begun. However, the applicant may submit a modification application at any time before the 18-month period has expired, requesting an extension of the approval period. The applicant may request more than one extension. Under no circumstances, however, can the total combined extension periods exceed 36 months from the original expiration date. Within S-DR, upon approval of a Willamette River Greenway Permit concurrently with Type V code amendments and other plan amendments, plan adoption, or zone change; the Willamette River Greenway Permit shall remain in effect so long as the S-DR zone remains in effect.

(Section 9.7340, see chart at front of Chapter 9 for legislative history from 2/26/01 through 6/1/02; and amended by Ordinance No. 20269, enacted November 25, 2002, effective December 25, 2002; amended by Ordinance No. 20513, enacted July 8, 2013, effective August 9, 2013; Ordinance No. 20693, enacted July 12, 2023, effective August 18, 2023.)